Status & timeline

Where we are, and what comes next

Developer-account enrollment, then the app build and store review follow.

Timeline durations are estimates

Status board

Eight workstreams. Amber items are needed from SDR.

Projected timeline

Critical path: SDR confirms the D-U-N-S details and provides assets, then Apple and Google Organization enrollment (estimate), then the Baron app build (about one week), then store review (about one week). Pick the date the assets arrive and the dates recompute.

Assets receivedMon, Oct 5Day 0
Developer accounts approved-estimate
Baron build-about 1 week, estimate
App launch-after store review, estimate

Latest date assets can arrive for an app launch by Oct 30 (estimate): -. The web track runs on its own fixed Conference MVP schedule and does not move with the date above.

Typical ranges (estimates)

General ranges only. Actual timing depends on Apple, Google and Dun & Bradstreet.

The conferences fall in weeks 3 and 4 of October; exact dates are to be confirmed. The web experience is the conference baseline. The app is a parallel track.